Insights

Managing an Electric Distributor's Portfolio to Increase Reliability and Capability

blue camper van with party lights

Overview

Our client, one of Texas' largest electric service providers servicing 75 counties, faced several critical challenges when trying to maintain and improve reliability and capability across an extensive network of over 5,100 miles of transmission lines and 380 substations. At the same time, they needed to adhere to strict schedules and budgets, a common issue in large-scale infrastructure projects, and navigate through organizational barriers while maintaining compliance with PMO governance.

On behalf of the client, PFES manages a portfolio of capital investments designed to increase the system’s reliability and capability and existing / future transmission, substation, and telecom facilities' infrastructure.

Within this scope, and using our experienced Senior Project Managers and Project Analysts, PFES has responsibility for establishing and maintaining portfolio schedules and budgets to ensure accurate reporting throughout the investment lifecycle. The budget and schedule requirements applied during this process are executed in accordance with the Transmission System Improvement Plan (TSIP) and Telecommunication Improvement Plan (TIP).

Our Approach

PFES utilized a portfolio management approach to align core stakeholders around a strategic vision that maximized capital investments in accordance with business goals and initiatives. In order to drive project success, our team members implemented creative, solution-driven strategies that helped navigate through organizational barriers while also maintaining compliance with PMO governance.

Our strategies involved developing new methods and approaches for addressing cost and schedule variances in order to maintain the integrity of the portfolio budget and forecast. These efforts have helped our client overcome operational challenges, improved accuracy of spend forecasting, and generated synergies across the organization through consistency of execution (i.e. standardized governance controls). PFES has also implemented IF / THEN risk tracking and mitigation strategies designed to minimize threats and maximize opportunities throughout the project lifecycle.

Outcome

PFES has added tremendous value to our client’s portfolio by providing agile project and portfolio management solutions that address client specific needs, while also ensuring that program performance aligns with internal processes and controls. This has allowed our team to influence the organization in a positive manner without disrupting the existing management structure.

Throughout the process, our client interactions with internal personnel have aided in helping a growing organization continue to develop and mature, improving the network's reliability and capability.

The Perfect Electric Portfolio Partner

Our team consists of industry heavyweights that bring substantial expertise to the table for our clients. We partner with you to reduce risk and uncertainty in your capital projects, delivering initiatives on time with significant cost savings while meeting industry and safety standards. Contact us today to find out how we can help.

Details
Date
April 26, 2024
Category
Case Studies
RElated Insights
hydrogen fuel pump
Case Studies

Advancing Hydrogen Power Generation: How PFES Project Management Expertise Enabled Collaborative Innovation in Tri-Gen Production

Read Article
group of business people meeting in modern conference room
Articles

Project Risk Management: A Strategic Imperative

Read Article

Let's Partner Together

Contact us today to learn how our expert services can guide your projects to successful completion.

Man sitting on turbine with hard hat looking at a field of turbines